Carpenter took 10.7 lacs and not completing my flat woodwork even after 4 months. Plus demanding 50K additional amount to complete the pending work.

Community Forums Legal Advice India Carpenter took 10.7 lacs and not completing my flat woodwork even after 4 months. Plus demanding 50K additional amount to complete the pending work.

Viewing 2 reply threads
  • Author
    Posts
    • #55356 Reply
      User_41712601
      Participant
        U
        User_41712601
        PARTICIPANT
        February 12, 2025 at 6:28 pm
        I bought a flat in Hyderabad and gave it to Carpenter for woodwork. The agreed amount was 11 lacs. I have already paid 10.7 lacs 4 months ago. Initial agreement was to hold a balance of 10% which should be given only after the completion of entire flat. But now, he is not only asking to pay everything even before completion but additional 50K ( sighting the reason for laminated I selected are costly ). We have the agreement only on white paper.

        Someone advise me on how to come out of this. A delay of month causes me rent of 20K too. ๐Ÿ™

      • #55358 Reply
        User_c4d4ff0c
        Participant
          U
          User_c4d4ff0c
          PARTICIPANT
          February 12, 2025 at 6:47 pm
          Do you have the receipt of the payment made to him?
          There after go to lawyer and explain him your situation and send a legal notice to the carpenter

          • #55360 Reply
            User_41712601
            Participant
              U
              User_41712601
              OP
              February 12, 2025 at 6:48 pm
              I have done all using PhonePe to his number.

            • #55359 Reply
              User_41712601
              Participant
                U
                User_41712601
                OP
                February 12, 2025 at 6:57 pm
                Soft copies those Receipts enough ?

            • #55357 Reply
              Silentsuhani990
              Participant
                S
                Silentsuhani990
                PARTICIPANT
                February 15, 2025 at 10:08 am
                Sorry but there is no way you are getting that money back.
                You may file a case but he will keep moving his house around and it will be tough for you to find/pin him